Holmewood Site Investment Plans

This website provides information on Magnavale’s investment plans for our Holmewood cold storage facility in Chesterfield.

The website will be updated throughout the construction phase with project completion targeted for November 2024.

Planning consent, which can be viewed here was granted for the extension of the existing facility in August 2021 by North East Derbyshire District Council.

Map of the site

Hard landscape

PROPOSED SECURITY FENCE

Soft landscape

PROPOSED SEMI NATURAL WOODLAND
National Vegetation Classification semi-natural woodland type W10

Soft landscape

PROPOSED WILDFLOWER GRASSLAND

Hard landscape

PROPOSED SHEET PILED RETAINING WALL

Hard landscape

PROPOSED ACOUSTIC FENCE

Soft landscape

EXISTING WOODLAND TO BE RETAINED

Soft landscape

PROPOSED GRASSLAND (MOWN)

Soft landscape

PROPOSED TREES
Betula pendula (Silver Birch)
Sorbus aucuparia (Rowan)

Hard landscape

PROPOSED REINFORCED CONCRETE RETAINING WALL

Latest Updates


7th May 2024

We would like to communicate the road closure that is a result of the Coldstore construction, this is from the 16th of May until the 30th of May, unless works are finished earlier. This closure is to facilitate pipes and cables crossing the road between our Coldstore 3 and Coldstore 5. The following is the location of the closure.

Below is a copy of the council’s notice.

27th March 2024

Following an investigation on the noise reported last night it would appear some equipment onsite was inadvertently left running through the night.

This will not happen again as the Site Manager has introduced a shutdown of works process being the last of the Site Foreman’s job prior to leaving the site.

We have been assured this will not happen again, and there should be no further noise throughout the night, during the weekend, or indeed the upcoming bank holidays.

Please accept our sincere apologies for any inconvenience caused regarding the above.

February 2024

We have had confirmation from Yorkshire Water that they will need to return to site to complete follow up works (2nd March). While this is not within the scope of our own works, we have requested that they keep noise to a minimum.


We have had confirmation from Yorkshire Water that they will be on-site to complete works this weekend (24th & 25 February). While this is not within the scope of our own works we have requested that they keep noise to a minimum.


Wednesday, February 7th, 2024:

Power floating Works Completion: These were successfully completed at 12:30am.

Lights Off: All lights on the site were turned off by 12:45am.

Concrete Pouring: The scheduled pour for February 8th went ahead as planned.

Thursday, February 8th - Friday, February 9th, 2024:

Due to the low temperatures on site, power floating operations extended until just after 05:00am on Friday morning.

Friday, February 9th, 2024:

The pour for today is ongoing and based on current temperature forecasts, our engineers and floor installers anticipate that power floating may continue until approximately 3:00am on Saturday, February 10th.

Important Notice:

No Further Planned Out of Hours Working: We are pleased to announce that there are no further out-of-hours working scheduled for the next 6 months.

We will continue to provide updates via our website. It is our priority to keep you informed about any future works that may impact you.

Once again, please accept our apologies for any inconvenience caused.


Dear all,

Many thanks for your messages about the work our contractor is currently carrying out on our Magnavale Chesterfield site and the disturbance it has caused to you all.

Please accept our sincere apologies for any inconvenience caused. We have begun pouring the first half of the top concrete slab on Monday 5/2/24 and this process involves power floating late into the evening and potentially early morning, whilst our contractors have advised that the noise of the power floats can travel, particularly as one end of the new building is currently open, unfortunately this was very difficult to predict the noise level experienced by you the residents.

Because this is a continuous process beginning at the start of the day, the moment the concrete is poured, the power floating needs to happen after the pour and given it is such a large area it will go into the late hours and early hours.

We have been advised that this work cannot be done any other way and we are extremely sorry to advise there is likely to be further disturbance to residents during normal out of ours working on Wednesday and Thursday evening this week with works hopefully completing by Friday of this week, weather permitting of course.

You will of course be pleased to hear, this is the last of the planned works which involve power floating out of agreed working hours.

Again, please accept our sincere apologies for the inconvenience this has caused.

Construction Timeline

October 2023

  • Completion of membrane to roof.
  • Yorkshire Water combined sewer diversion works.
  • External drainage.
  • External concrete to yard areas.
  • Internal services works.
  • Concrete slab to chill area.

November 2023

  • Yorkshire Water combined sewer diversion works.
  • External drainage.
  • External concrete to yard areas.
  • Internal services works.
  • Pipework at roof level.

December 2023

  • Yorkshire Water combined sewer diversion works.
  • External drainage.
  • External concrete to yard areas.
  • Lighting and Power.
  • Refrigeration Pipework.

January 2024

  • Yorkshire Water combined sewer diversion works.
  • Racking rails installation.
  • Internal Concrete top slab.
  • Lighting and Power.
  • Refrigeration Pipework and chillers.
  • Foundations of remainder of building.

February 2024

  • Steelwork to remainder of building to be erected.
  • Plantroom building works commence.
  • Internal Concrete top slab.
  • Lighting and Power.
  • Refrigeration Pipework and chillers.

March 2024

  • Wall and roof cladding to remainder of building.
  • Plantroom building works.
  • Car Park groundworks.
  • Lighting and Power.
  • Refrigeration Pipework and chillers.

April 2024

  • Concrete yard works.
  • Plantroom floors install.
  • Chiller room concrete slabs to be cast.
  • Emergency signage install.
  • Drainage and heating install.
  • Plant room and main building cladding.
  • Racking bases install.
  • Docking bay doors install.
  • Top floor concreting works.

May 2024

  • Concrete yard works.
  • Plantroom floors complete.
  • Chiller Room Concrete slabs to be completed.
  • Drainage and heating completion.
  • Plant room and main building cladding completed.
  • Racking bases install to continue.
  • Docking bay doors installation to continue.
  • Floor concreting to extend to remainder of required internal areas.

June 2024

  • TBA